Refurbishment Works
1. Project: Marks & Spencer, Braehead, Glasgow: Extension & Refurbishment
2. Main Contractor: Morgan Ashurst
This project required the complete removal of existing floor finishes including wood, ceramic tiles, carpet and vinyl floorcoverings. With a tight contract programme, it was necessary to use a "Terminator" mechanical ride-on stripping machine. The existing subfloor was extensively repaired using an epoxy resin primer and rapid drying self-levelling compound prior to the new floorcoverings being installed. To accommodate the clients requirements all work was carried out on a nightshift basis to allow the store to maintain normal trading times and condition with minimal disruption. The project was completed in 6 months in line with the agreed programme.
The approximate contract value was £800,000.
A summary of the materials used in the project were: