New Build Works
1. Project: Glasgow Primary Schools - "Primary Visions " - Glasgow City Council
2. Main Contractor: City Building (Glasgow) LLP
We were privileged to be awarded the contract for the supply and installation of all floorcoverings and accessories on the above project. The Framework Agreement with City Building (Glasgow) LLP involved 18 new build Primary Schools. Works commenced in May 2004 and are scheduled for completion in March 2010. They have an approximate value of £2,000,000. Approximately 75,000m² of floorcoverings will be installed together with all relevant preparatory works including surface dpms. The schools concerned were:
|
|
|
An approximate split of the materials installed were:
|
|
|
|
|
|
|